MGE™ Galaxy™ 3500 10-40 kVA 380/400/415 V, 10-30 kVA 208/220 V Battery Installation16
Connect Power in Installations with Cables
Install power cables
See “Recommended cable sizes” on page 23.
Install power cables between the UPS and the XR Battery Enclosure.
1. In the UPS, feed the cable
up through the conduit box
or through the transparent
cable route bracket (not
shown).
2. Connect the Bat+, Bat-, and
N cables to the busbars in
the UPS.
3. Secure the cables to the
perforated bracket with
cable ties.
4. Equip the cable with
conduits (if applicable).
5. In the XR Battery
Enclosure, feed the cable
up through the conduit box
(if applicable) to the cable
landing area.
6. Connect the (+) cable to
busbar no. 1 (+), connect
the N cable to busbar no. 4
(N), and the (-) cable to
busbar no. 6 (-).
7. Secure the cable to the
perforated bracket with
cable ties.
8. Attach the top part of the
conduit box (if applicable).
BAT
BAT
BAT
BAT
UPS rear view.
XR Battery Enclosure rear view
To XR2