22 InfraStruXure System – Service Manual – Installation and Start-Up 990-1467C
Attach the PDU, UPS, and XR Battery
Enclosure
1. Move the PDU, Symmetra PX UPS, and XR Battery Enclosures into position, aligning the holes in
the adjacent side panels.
2. Level the PDU, Symmetra PX UPS, and XR Battery Enclosure by using a level and adjusting the
leveling feet on each enclosure.
3. Thread the chase nipple (part number: 820-0071) through the opening in the adjacent side panels of
the enclosures. The following enclosures will need to be attached:
• An adjacent PDU and UPS
• An adjacent XR Battery Enclosure and UPS
• Adjacent XR Battery Enclosures
4. Tighten the lock-nut and the bushing on the chase nipple.
psx0023a