Start-Up Procedure
56 InfraStruXure System – Service Manual – Installation and Start-Up 990-1467C
Verify proper voltage and phase rotation on the PDU
1. Close (turn ON) the Q1 circuit breaker on the InfraStruXure PDU to apply power to the UPS.
2. Ensure A-B-C clockwise rotation at the UPS input bus bars, using a phase rotation meter.
3. Verify proper voltage is present at the UPS input bus bars (208V, metered phase-to-phase),
using a true RMS voltmeter.
4. Ensure A-B-C clockwise rotation at the top of the PDU bypass switch, using a phase rotation
meter.
5. Verify proper voltage is present at the top of the PDU bypass switch (208V, metered phase-to-
phase), using a true RMS voltmeter.
Warning: The voltage for the bypass feed can only be 208V, phase-to-phase.
2. Set the UPS System Enable switch to the
OFF position.
3. Set the XR Battery Enclosure DC Disconnect
circuit breaker to the OFF position.